Stage 1 — Order Confirmation & Engineering Review
1–3 Days
Upon receiving your order, our engineering team conducts a full technical review, confirms custom specifications (voltage, belt speed, paper width, etc.), and locks the production schedule. Our in-house design team eliminates the back-and-forth delays common with trading companies.
🔧
Stage 2 — Raw Material & Component Preparation
3–7 Days
Thanks to our deep-rooted supplier network in Dongguang's industrial cluster, critical materials — structural steel, precision rollers, electrical components — are procured and pre-staged within days. We maintain strategic stock of high-frequency parts to prevent supply chain delays.
⚙️
Stage 3 — CNC Machining & Parts Fabrication
7–20 Days
All structural frames, rollers, gear systems, and precision components are manufactured in our own CNC workshops. Because we do not outsource fabrication, tolerances are controlled to ±0.02mm, and production schedules are never disrupted by a third-party factory's workload.
🏭
Stage 4 — Assembly & System Integration
5–15 Days
Dedicated assembly teams in each of our three factories handle machine integration with strict work-order tracking. Real-time production progress is monitored by our project managers, and customers can request live video updates at any assembly stage.
✅
Stage 5 — Factory Acceptance Testing (FAT)
2–5 Days
Every machine undergoes a full-load running test before shipment. We record video documentation of the FAT and share it with the buyer. Machines that do not meet our performance standards are corrected before leaving the factory — not after arrival at your site.
🚢
Stage 6 — Export Packaging & Shipment
2–4 Days
Machines are professionally packed in export-grade wooden crates with anti-rust treatment, moisture barriers, and shock-absorbing supports. We coordinate directly with freight forwarders to secure the earliest available vessel, with full shipping documentation provided promptly.